Construction Projects

On February 17, 2025, district taxpayers voted on a multi-question special election ballot. With 65.5% approval, Question 1—a $99.7 million package that will address critical projects over the next 1-5 years—received strong support, while the other two questions fell short with 59.1% and 43.0% approval.

This section of our website is dedicated to transparency, offering you detailed updates on the progress and status of the projects funded by Question 1:

NOTE: As projects kickoff, a dedicated page will be added to this section of the website, where all phases of the construction process for that project will be documented. 

Project Timeline & Cost Estimates

Project Cost Estimate

Estimated
Start Date

Estimated Completion Date
Horace HS: completion of classroom "shells" $2,221,875 Spring 2025 End of Year 2025
Heritage MS $22,610,203 Late Summer 2025 Summer 2027
Inclusive Playground @ ECC $550,000 Fall 2025 Summer 2026
South Elementary Expansion & Renovation $17,851,155 Early Spring 2026 End of Year 2028
Horace HS: full build-out with multipurpose room $33,808,671 Late Spring 2026 Summer 2028
Districtwide Renovations: special education, safety and security, restrooms, multipurpose room @ West Fargo HS $13,489,330 Fall 2026 School-Specific
Early Childhood Special Education Program Expansion $9,168,766 TBD TBD

 

Updated: 2/24/25