Construction Projects
On February 17, 2025, district taxpayers voted on a multi-question special election ballot. With 65.5% approval, Question 1—a $99.7 million package that will address critical projects over the next 1-5 years—received strong support, while the other two questions fell short with 59.1% and 43.0% approval.
This section of our website is dedicated to transparency, offering you detailed updates on the progress and status of the projects funded by Question 1:
- Inclusive Playground at Early Childhood Center
- High School Multipurpose Rooms
- Restroom Improvements
- Special Education Improvements
- Safety & Security Upgrades
- Renovation & Expansion of South Elementary
- Expansion of Early Childhood Special Education Services
- Completion of Heritage Middle School
- Completion of Horace High School
Inclusive Playground at Early Childhood Center
High School Multipurpose Rooms
Restroom Improvements
Special Education Improvements
Safety & Security Upgrades
Renovation & Expansion of South Elementary
Expansion of Early Childhood Special Education Services
Completion of Heritage Middle School
Completion of Horace High School
Project Timeline & Cost Estimates
Project | Cost Estimate |
Estimated |
Estimated Completion Date |
---|---|---|---|
Horace HS: completion of classroom "shells" | $2,221,875 | Spring 2025 | End of Year 2025 |
Heritage MS | $22,610,203 | Late Summer 2025 | Summer 2027 |
Inclusive Playground @ ECC | $550,000 | Fall 2025 | Summer 2026 |
South Elementary Expansion & Renovation | $17,851,155 | Early Spring 2026 | End of Year 2028 |
Horace HS: full build-out with multipurpose room | $33,808,671 | Late Spring 2026 | Summer 2028 |
Districtwide Renovations: special education, safety and security, restrooms, multipurpose room @ West Fargo HS | $13,489,330 | Fall 2026 | School-Specific |
Early Childhood Special Education Program Expansion | $9,168,766 | TBD | TBD |
Updated: 2/24/25